Admiral Park Infrastructure
GUERNSEY
JPC was appointed as Project Manager and Employer’s Agent to deliver the infrastructure associated with the first phase of the Admiral Park development.
Project Summary
The infrastructure works were procured as an enabling works package to unlock the development site and comprised of:
-
Service diversions and demolitions
-
Creation of temporary signals at adjacent road junctions
-
Creation of a new cycle lane
-
Road widening, additional lane creation and pavement realignment
-
Main junction upgrade to permanent traffic signals.
-
Temporary works as necessary to ensure all highways remained open during the works
As part of the brief, JPC engaged a specialist highways design consultant to prepare the necessary highways designs, traffic surveys and travel plans.
Local contractors were awarded the contract for the complete of the works under a JCT Form of Contract.
Working with the lead client and their consultant team, JPC defined the requirement, procured the works and managed the project through to completion of construction.