JPC was engaged to provide Primavera P6 Programme Management of the Mechanical and Electrical scope of works covering design, procurement, manufacture, installation and commissioning for the new Avera Warehouse and Simulator Training Buildings at Hinkley Point C Nuclear Power Station.
Project Summary
Hinkley Point C is one of the largest construction projects in Europe. It is a highly complex and technologically advanced engineering project, which, when completed in 2025, is expected to provide 7 percent of the UK’s electricity consumption.
Considered vital to the operational success of Hinkley Point C, the ‘Simulator Training Centre’ is scheduled as one of the first permanent buildings to be constructed on the site and will allow operatives to learn how to control nuclear reactors in a virtual environment.
JPC’s involvement with the project spanned from appointment in December 2017 to project handover in June 2021.